SILVER LINE COURTHOUSE STATION WATERPROOFING RESILIENCY AND REPAIRS
Boston, MA
Advertisement Date |
10/8/2020 |
Pre-Bid Meeting Date & Time | 10/22/2020 at 2:00 PM |
Bid Opening Date | 11/19/2020 |
Contract Number | X02CN04 |
Class | CLASS 1, GENERAL TRANSIT CONSTRUCTION, $20,000,000 AND CLASS 7 – BUILDINGS, $20,000,000 |
Project Value | $25,160,000.00 |
DBE Goal | 0 % |
Scope of Work:
The Work consists of waterproofing and waterproofing repairs, replacement of sump pumps, replacement of mechanical systems and duct work, replacement of electrical equipment and installation of new conduits, installation of an access door and sump pump in the air intake structure, drain line cleaning, and replacement of damaged architectural features.
All PDFs can be viewed with Adobe Acrobat Reader version 4.0 or higher.
View Complete Notice to Bidders
Awaiting Receipt of Comparison of Bids Report
X02CN04 Planholders List
X02CN04 Planholders List (Printer Friendly)
Apparent Low Bidder | Bid Amount |
BOND Civil & Utility Construction, Inc. | $26,921,663.05 |
Bid Responses | Bid Amount |
J. F. White Contracting Co. | $27,435,524.00 |
Mccourt Construction Co. Inc | $30,849,505.00 |