MBTA Phase 2B- Systemwide Transformer Replacement
Boston, Cambridge, Newton, Quincy & Brookline, Massachusetts
Advertisement Date |
3/14/2019 |
Pre-Bid Meeting Date & Time | 03/29/2019 at 1:00 PM |
Bid Opening Date | 4/30/2019 |
Contract Number | P62CN01 |
Class | 5 - ELECTRICAL |
Project Value | $9,540,110.00 |
DBE Goal | 12 % |
Scope of Work:
The work comprises electrical, civil, structural and architectural construction services for the replacement of 11 rectifier-transformers and associated items. The work of this Contract includes but is not limited to equipment procurement, furnishing all necessary labor and material to the complete and satisfactory execution of the Work in conformance with Drawings and Specifications for the Phase 2B – Systemwide Transformer Replacement Project.
All PDFs can be viewed with Adobe Acrobat Reader version 4.0 or higher.
View Complete Notice to Bidders
Comparison of Bids Report for Contract P62CN01 (75.68kb) updated Tuesday, April 30, 2019
P62CN01 Planholders List
P62CN01 Planholders List (Printer Friendly)
Apparent Low Bidder | Bid Amount |
Mass Bay Electrical Corp. | $10,746,810.00 |
Bid Responses | Bid Amount |
Fischbach And Moore Electric | $11,114,110.00 |
Mcdonald Electrical Corporation | $11,959,984.00 |
Dagle Electrical Construction Corp. | $11,978,110.00 |