Bidding and Solicitations > Bid Responses

South Coast Rail, Fall River Secondary Commuter Rail Expansion Project


<<Back to Bid Responses

Berkley to Fall River, MA

Advertisement Date
2/14/2020
Pre-Bid Meeting Date & Time 03/04/2020 at 9:00 AM
Bid Opening Date 5/7/2020
Contract Number K78CN03
Class CLASS 1 – GENERAL TRANSIT CONSTRUCTION $50,000,000, CLASS 3 – TRACK WORK, $30,000,000, CLASS 7 – BUILDINGS, $10,000,000
Project Value $164,561,323.00
DBE Goal 0 %

Scope of Work:

The Work involves three major elements: (1) the construction of approximately twelve miles of new trackway along the existing Fall River Secondary right of way from Berkley to Fall River, (2) the construction of two commuter rail passenger stations, and (3) the construction of an end of the line layover facility.

All PDFs can be viewed with Adobe Acrobat Reader version 4.0 or higher.

View Complete Notice to Bidders (PDF)View Complete Notice to Bidders

View Complete Notice to Bidders (PDF)Comparison of Bids Report for Contract K78CN03 (58.25kb) updated Thursday, May 7, 2020

K78CN03 Planholders List    K78CN03 Planholders List (Printer Friendly) K78CN03 Planholders List (Printer Friendly)

Apparent Low Bidder Bid Amount
Skanska DW White JV $158,975,000.00
Bid Responses Bid Amount
White-Manafort, JV $163,967,871.00
The Middlesex Corp. $168,469,000.00
Barletta Heavy Division, Inc. $170,928,000.00
Walsh-RCC, JV $191,754,031.00
Lane-Delta SCR JV $217,208,603.50