Bidding and Solicitations > Bid Responses

South Coast Rail, Building Demolition


<<Back to Bid Responses

Southeastern, Massachusetts

Advertisement Date
1/31/2020
Pre-Bid Meeting Date & Time 02/14/2020 at 9:00 AM
Bid Opening Date 2/27/2020
Contract Number K78CN02
Class 8 - DEMOLITION
Project Value $2,662,429.00
DBE Goal 0 %

Scope of Work:

The Work involves the demolition of buildings and other structures located on MBTA controlled property at nine separate locations in Middleborough, Taunton, Berkley, Freetown, Fall River, and New Bedford. This demolition work is taking place in preparation for commuter rail system construction.

All PDFs can be viewed with Adobe Acrobat Reader version 4.0 or higher.

View Complete Notice to Bidders (PDF)View Complete Notice to Bidders

View Complete Notice to Bidders (PDF)Comparison of Bids Report for Contract K78CN02 (73.54kb) updated Thursday, February 27, 2020

K78CN02 Planholders List    K78CN02 Planholders List (Printer Friendly) K78CN02 Planholders List (Printer Friendly)

Apparent Low Bidder Bid Amount
D. W. WHITE CONSTRUCTION INC. $1,743,721.00
Bid Responses Bid Amount
Costello Dismantling Co., Inc. $1,829,261.00
J.R. Vinagro Corp. $1,840,771.00
American Environmental, Inc. $2,542,271.00
S & R CORP., FNA STEVEN & ROGER $2,618,606.00
J. H. Lynch & Sons Inc. $2,694,221.00
Manafort Brothers Incorporated $2,877,901.00
MCCONNELL ENTERPRISES INC. $2,923,000.00