Bidding and Solicitations > Bid Responses

SILVER LINE COURTHOUSE STATION NORTHEAST HEADHOUSE


<<Back to Bid Responses

Boston, MA

Advertisement Date
11/30/2020
Pre-Bid Meeting Date & Time 12/09/2020 at 2:00 PM
Bid Opening Date 2/11/2021
Contract Number E59CN01
Class CLASS 1, GENERAL TRANSIT CONSTRUCTION, $3,000,000 AND CLASS 7 – BUILDINGS, $11,000,000
Project Value $14,500,000.00
DBE Goal 0 %

Scope of Work:

The work consists of the construction of two new headhouses, one with a two-stop BCIL elevator and the second containing a transit rated escalator and stairs. Both headhouses will be of curtainwall on stone veneer concrete base plinth with flat roofs and both will be equipped with a demountable flood control panel sytsem outside the door thresholds. Both headhouses will provide access from the sidewalk level to the existing Courthouse Station concourse. There is electrical and mechanical work to tie in to the existing Station infrastructure. After the headhouses are granted TCO’s the last phase will be to demolish the existing emergency egress stair and exterior headhouse enclosure.

All PDFs can be viewed with Adobe Acrobat Reader version 4.0 or higher.

View Complete Notice to Bidders (PDF)View Complete Notice to Bidders

View Complete Notice to Bidders (PDF)Comparison of Bids Report for Contract E59CN01 (37.90kb) updated Thursday, February 11, 2021

E59CN01 Planholders List    E59CN01 Planholders List (Printer Friendly) E59CN01 Planholders List (Printer Friendly)

Apparent Low Bidder Bid Amount
Mccourt Construction Co. Inc $15,292,000.00
Bid Responses Bid Amount
BOND Civil & Utility Construction, Inc. $16,243,000.00
Wes Construction Corp. $16,356,000.00
Skanska Usa Civil Northeast, Inc. $16,890,000.00
Sps New England, Inc. $17,378,000.00
J. F. White Contracting Co. $18,717,943.00