Awarded Contract: P40CN01
<< Back to Awarded MBTA Contracts
MBTA Redline Substations, Traction Power Upgrade,
Boston & Quincy, Ma
Advertisement Date | 3/15/2011 |
Pre-Bid Meeting Date & Time | March 30, 2011 at 10:00 AM |
Bid Opening Date | 5/12/2011 |
Contract Number | P40CN01 |
Class | CLASS 5 - ELECTRICAL, PROJECT VALUE $ 20,598,000.00 AND CLASS 1 – GENERAL TRANSIT CONSTRUCTION $ 3,000,000.00 |
Project Value | $20,598,000.00 |
DBE Goal | 18 % |
Scope of Work:
The General scope of the work under this Contract is for the furnishing of labor, material and equipment to complete the upgrade to dc traction power equipment at five MBTA Substations on the MBTA Red Line in conformance with Drawings and Specifications for the Red Line Traction Power Upgrade Project.
General Contractor | Contract Value |
J.F. White Contracting Company | $13,047,500.00 |
Notice to Proceed Date: | 9/22/2011 |
Projected Completion Date: | 3/23/2015 |
Bid Responses | Bid Amount |
J.F. White Contracting Company | $13,047,500.00 |
Siemens | $14,618,857.52 |
Mass Electric Construction Co. | $15,216,990.00 |
JV: Barletta/Fischbach and Moore | $15,804,750.00 |
Mass. Bay Electrical Corp. | $20,830,000.00 |
All PDFs can be viewed with Adobe Acrobat Reader version 4.0 or higher.
View Complete Notice to Bidders
Comparison of Bids Report for Contract P40CN01 (98.30kb) updated Monday, May 23, 2011
P40CN01 Planholders List
P40CN01 Planholders List (Printer Friendly)
Notice
The posting of on-line information on the Massachusetts Bay Transportation Authority
Web Page on Massachusetts Bay Transportation Authority construction contracts
is being made solely for informational purposes and is subject to change, without
notice.
The posting of on-line information shall not be construed as an indication that any person or entity accessing such information is eligible to purchase plans and specifications under M.G.L. c.29, 8B.
The posting of on-line information does not relieve prospective bidders of their obligation to review and become familiar with the Contract Documents, as bid, including, but not limited to, the obligation to inspect plans, specifications and any addenda. The Contract Documents as bid shall supersede and take precedence over any information posted by the Massachusetts Bay Transportation Authority on the Massachusetts Bay Transportation Authority Web Page.
The posting of on-line information does not relieve prospective bidders of
their obligation to consult the Central Register published by the Secretary
of State's Office pursuant to M.G.L. c. 149 §44J and c.9, §20A for
official information concerning any Massachusetts Bay Transportation Authority
construction contract. The information published in the Central Register shall
supersede and take precedence over any information posted by the Massachusetts
Bay Transportation Authority on the Massachusetts Bay Transportation Authority
Web page.
Bidders are advised that they should have representation at this tour as no
extra visits are planned.