Bidding and Solicitations > Awarded Contracts

Awarded Contract: G80CN01


<< Back to Awarded MBTA Contracts

Old Colony Commuter Rail Tie Replacement Project

Southeastern, MA

Advertisement Date 6/28/2010
Pre-Bid Meeting Date & Time July 08, 2010 at 10:00 AM
Bid Opening Date 8/12/2010
Contract Number G80CN01
Class 3 - TRACKAGE
Project Value $24,649,300.00
DBE Goal 5 %

Scope of Work:

The work consists of replacing existing concrete ties with new timber ties; disposal of concrete ties; surface and align track; upgrade existing grade crossing surfaces on the Old Colony Commuter Rail Lines; and surface preparation and field painting of exposed surfaces for the Union Street Bridge will also be included. The limits of the tie replacement Work is summarized as follows: • Old Colony Main Line – approximately 4.1 miles of track extending from Boston to Braintree • Old Colony Plymouth Line – approximately 26.0 miles of track extending from Braintree to Plymouth • Old Colony Plymouth Line (Kingston Branch) – approximately 1.7 miles of track in Kingston • Old Colony Middleborough Line – approximately 25.1 miles of track extending from Braintree to Lakeville

General Contractor Contract Value
J.F. White Contracting Company $34,862,150.00

Notice to Proceed Date: 10/22/2010
Projected Completion Date: 12/20/2011

Bid Responses Bid Amount
J.F. White Contracting Company $34,862,150.00
JV: Jay Cashman, Inc./Balfour Beatty $37,323,000.00
Barletta Heavy Division Inc. $39,395,750.00
Kiewit Infrastructure $47,596,600.00

All PDFs can be viewed with Adobe Acrobat Reader version 4.0 or higher.

View Complete Notice to Bidders

View Complete Notice to Bidders (PDF)Comparison of Bids Report for Contract G80CN01 (47.82kb) updated Friday, August 13, 2010

G80CN01 Planholders List    G80CN01 Planholders List (Printer Friendly) G80CN01 Planholders List (Printer Friendly)

Notice
The posting of on-line information on the Massachusetts Bay Transportation Authority Web Page on Massachusetts Bay Transportation Authority construction contracts is being made solely for informational purposes and is subject to change, without notice.

The posting of on-line information shall not be construed as an indication that any person or entity accessing such information is eligible to purchase plans and specifications under M.G.L. c.29, 8B.

The posting of on-line information does not relieve prospective bidders of their obligation to review and become familiar with the Contract Documents, as bid, including, but not limited to, the obligation to inspect plans, specifications and any addenda. The Contract Documents as bid shall supersede and take precedence over any information posted by the Massachusetts Bay Transportation Authority on the Massachusetts Bay Transportation Authority Web Page.

The posting of on-line information does not relieve prospective bidders of their obligation to consult the Central Register published by the Secretary of State's Office pursuant to M.G.L. c. 149 §44J and c.9, §20A for official information concerning any Massachusetts Bay Transportation Authority construction contract. The information published in the Central Register shall supersede and take precedence over any information posted by the Massachusetts Bay Transportation Authority on the Massachusetts Bay Transportation Authority Web page.

Bidders are advised that they should have representation at this tour as no extra visits are planned.