Project NameOak Grove Orange Line Station Station Platform and Pedestrian Bridge Structural Repairs
Project LocationMalden, MA
Contract NumberS33CN02
Class1 - GENERAL TRANSIT CONSTRUCTION
Project Value$2,240,000.00
DBE Goal18%

Scope of Work

Work consists of the following: concrete hydrodemolition of existing platform topping slab, construction of a new concrete topping slab, removal of existing shoring at the east pedestrian bridge, removal and replacement of expansion joints, removal and replacement of guardrails at the station platform, and construction of a new accessible bathroom installed in the existing “Safe” room

Note: Contract specifications and drawings are available for download from an MBTA FTP site.
Click here to be put on the Planholders list, and request a copy of the contract specifications and drawings.

Send Sealed Bids to:

All bids must be submitted electronically at: www.Bidx.com

Bids Must Be Received By: June 28, 2012 At 2:00 PM

Immediately thereafter, the Bids will be opened and read publicly on a virtual on-line meeting.

Authorization for the Bidders to view the site of work on the MBTA's property shall be obtained by:

Project ManagerWei Lee Shia
500 Arborway, Jamaica Plain, MA 02130
Telephone Number617-222-6213
Site Tour Date & Time*June 13, 2012 at 10:00 AM
Site Tour LocationOak Grove Station on Washington Street, Malden, Massachusetts
Pre-Bid Meeting Date & Time **June 15, 2012 at 10:00 AM
Pre-Bid Meeting Location500 Arborway, Jamaica Plain, Conference Room # 1
Documents AvailableJune 04, 2012

*. Bidders are advised that they should have representation at this tour as no extra visits are planned.
**. Any request for interpretation of the Plans and Specifications should be submitted in writing at the same time.