Project NameEverett Maintenance Facility Tire and Battery Relocation Project
Project LocationEverett, Ma
Contract NumberR19CN04

Scope of Work

The project consists of converting existing areas of the Bus Overhaul Shop Building in the Everett Maintenance Facility into tire and battery repair shops. The work will include demolition of existing features and replacement with new features as required, as well as furnishing and installing equipment to provide power, lighting, fire protection and ventilation for these two new rooms. The work also includes the relocation of existing equipment at the MBTA’s Water Street Facility in Cambridge to the Everett Maintenance Facility.

Note: Contract specifications and drawings are available for download from an MBTA FTP site.
Click here to be put on the Planholders list, and request a copy of the contract specifications and drawings.

Send Sealed Bids to:

All bids must be submitted electronically at: www.Bidx.com

Bids Must Be Received By: February 13, 2007 At 2:00 PM

Immediately thereafter, the Bids will be opened and read publicly on a virtual on-line meeting.

Authorization for the Bidders to view the site of work on the MBTA's property shall be obtained by:

Project ManagerWei-Lee Shia
500 Arborway, Jamaica Plain, MA 02130
Telephone Number617-222-6123
Site Tour Date & Time*January 22, 2007 at 10:00 AM
Site Tour Locationin front of the Everett Maintenance Facility Guard House, on Broadway, Everett, Massachusetts
Pre-Bid Meeting Date & Time **January 24, 2007 at 10:00 AM
Pre-Bid Meeting LocationMBTA, 500 Arborway, Jamaica Plain, Massachusetts 02130
Documents AvailableJanuary 12, 2007

*. Bidders are advised that they should have representation at this tour as no extra visits are planned.
**. Any request for interpretation of the Plans and Specifications should be submitted in writing at the same time.